Operating theatre handover: what to check before you sign

The tests, readings and certificates a new or refurbished theatre should come with, system by system, and where handovers usually slip.

The short answer

In short

Accept an operating theatre on test evidence, not on how it looks. Before you sign, the handover file should prove the ventilation (air changes, pressure, HEPA integrity, temperature and humidity), the medical gas tests, the isolated power supply and its alarms, and the as-built drawings. On KRM theatres these certificates go into one handover dossier.

Ventilation references
ASHRAE 170 or HTM 03-01, as stated in the approved design
Medical gases
HTM 02-01 tests, quality signed by a Quality Controller (MGPS)
Electrical
IEC 60364-7-710 Group 2: medical IT system with insulation monitoring
KRM experience
15+ operating theatres delivered by KRM and its leadership team

Questions answered

Frequently asked questions

How many air changes does an operating theatre need?

It depends on the design basis. ASHRAE 170 sets at least 20 air changes per hour in total for an operating room, 4 of them outdoor air. HTM 03-01 uses 22 air changes per hour for a conventionally ventilated theatre. The approved design should say which one applies.

Who signs off medical gas quality before a theatre is used?

Under HTM 02-01 the quality tests are carried out by a Quality Controller (MGPS), who checks the gas at the outlets against the pharmacopoeia. The results sit alongside the pipeline tests for leakage, cross-connection, flow and gas identity.

What is an IPS in an operating theatre?

An isolated power supply, called a medical IT system in IEC 60364-7-710. An isolating transformer feeds the equipment around the patient and an insulation monitor alarms when insulation resistance falls to 50 kOhm, so a first fault warns staff instead of cutting power.

Is microbiological air sampling required at handover?

Not normally. HTM 03-01 says it is needed only when the contract specifies it. For ultra-clean theatres the guidance expects air at the wound below 10 colony forming units per cubic metre during surgery, so check what your specification asks for.